Alabama’s Lake Thurlow To Refill With New Spillway Gates
By Stacy White and Justin Averette
Lake Thurlow is coming back up following completion of a two-year project to replace spillway gates at Thurlow Dam.
Lake levels are scheduled to begin rising on Tuesday, Oct. 29, reaching normal full pool by Thursday, Oct. 31.
The drawdown was needed to replace the dam’s 36 spillway crest gates, known as flashboards, which were installed in the 1920s. The replacements, called Obermeyer gates, are more efficient than the old system and will provide greater control to manage water resources, according to Thurlow Dam Superintendent Joel Johnson.
Please CLICK HERE to finish reading the article on the Alabama NewsCenter website.